Overview

Control limits on a control chart show the range a stable process normally stays within. Points outside them signal that something has changed.

Enter the process mean, the process standard deviation, the sigma multiplier (usually 3) and the subgroup size.

Worked examples

InputsResult
Process Mean42Process Std Dev6Sigma Multiplier3Subgroup Size5Center line: 42UCL: 50.05LCL: 33.95Subgroup SE: 2.68
Show 2 more examples
Process Mean100Process Std Dev2Sigma Multiplier3Subgroup Size4Center line: 100UCL: 103LCL: 97Subgroup SE: 1
Process Mean10Process Std Dev0.5Sigma Multiplier2Subgroup Size1Center line: 10UCL: 11LCL: 9Subgroup SE: 0.5

Center line by process mean

With the calculator's starting values, the center line is 42. The table shows how it changes with the process mean.

Process MeanCenter line
3030
4040
42starting value42
5050
6060

Other inputs: Process Std Dev: 6 · Sigma Multiplier: 3 · Subgroup Size: 5. Change them in the calculator above for your own numbers.

How it works

For an X-bar chart, the limits are the mean ± k × σ ÷ √n, where n is the subgroup size. With 3-sigma limits, a stable process rarely produces a point outside them, about 0.27% of the time. Control limits come from the process, not from specifications.

The formula

UCL = mean + k × σ ÷ √n
kSigma multiplier, usually 3
nSubgroup size

Practical tips

  • A mean of 42, σ = 6 and subgroups of 5 give limits of 33.95 to 50.05.
  • For individual readings, use n = 1.
  • Control limits aren't spec limits. A process can be in control and still make out-of-spec parts.

Frequently asked questions

Why 3 sigma?

It balances false alarms against missing real changes, a convention from Walter Shewhart.

What's the difference between control and spec limits?

Control limits describe what the process does. Spec limits describe what the customer needs.

How should σ be estimated?

Usually from the average range or standard deviation within subgroups.